一起答

2010年下半年软考系统集成项目管理工程师-上午试卷(标准答案+解析版)

  • 卷面总分:75分
  • 浏览次数:0
  • 测试费用:免费
  • 答案解析:是
  • 练习次数:23次
  • 作答时间:150分钟
试卷简介
2010年下半年软考系统集成项目管理工程师-上午试卷(标准答案+解析版):本试卷总分75分;共有一类型题目
部分试题预览
  1.  ● Plan Quality is the process of identifying quality requirements and standards for the project and product, and documenting how the project will demonstrate compliance.(75) is a method that analyze all the costs incurred over the life of the product by investment in preventing nonconformance to requirements, appraising the product or service for conformance to requirement, and failing to meet requirements.

    (75)

    • A.Cost-Benefit analysis              
    • B.Control charts  
    • C.Quality function deployment       
    • D.Cost of quality analysis
  2.  ● Perform Quality Control is the process of monitoring and recording results of executing the Quality Plan activities to assess performance and recommend necessary changes.(74) are the techniques and tools in performing quality control.

    Statistical sampling ①     Run chart ②  

    Control charts ③         Critical Path Method ④  

    Pareto chart ⑤                Cause and effect diagrams ⑥  

    (74)

    • A.①②③④     
    • B.②③④⑤      
    • C.①②③⑤⑥   
    • D.①③④⑤⑥
  3.  ● Business intelligence (BI) is the integrated application of data warehouse, data mining and (73).

    (73)

    • A.OLAP        
    • B.OLTP        
    • C.MRPII        
    • D.CMS.
  4.  ● OSI is a theoretical model that shows how any two different systems can communicate with each other.Router, as a networking device, operate at the  (71)  layer of the OSI model.

    (71)

    • A.transport       
    • B.application     
    • C.network       
    • D.physical  
  5.  ● Most of the host operating system provides a way for a system administrator to manually configure the IP information needed by a host.Automated configuration methods, such as  (72) , are required to solve the problem.

    (72)

    • A.IPsec        
    • B.DHCP        
    • C.PPTP        
    • D.SOAP
  6.  ● 在质量管理中可使用下列各图作为管理工具,这 4 种图按顺序号从小到大依次是(68)

    (68)

    • A.相互关系图、控制图、流程图、排列图
    • B.网络活动图、因果图、流程图、直方图
    • C.网络活动图、因果图、过程决策程序图、直方图
    • D.相互关系图、控制图、过程决策程序图、排列图
  7.  ● 甲公司最近中标某市应急指挥系统建设,为保证项目质量,项目经理在明确系统功能和性能的过程中,以本省应急指挥系统为标杆,定期将该项目的功能和性能与之比较。这种方法属于(69) 。

    (69)

    • A.实验设计法   
    • B.相互关系图法  
    • C.优先矩阵图法  
    • D.基准比较法
  8.  ● 关于项目质量审计的叙述中,(70)是不正确的。

    (70)

    • A.质量审计是对其他质量管理活动的结构化和独立的评审方法
    • B.质量审计可以内部完成,也可以委托第三方完成
    • C.质量审计应该是预先计划的,不应该是随机的
    • D.质量审计用于判断项目活动是否遵从于项目定义的过程
  9.  ● 某公司最近承接了一个大型信息系统项目,项目整体压力较大,对这个项目中的变更,可以使用(65)等方式提高效率。

    ①分优先级处理 ②规范处理 ③整批处理 ④分批处理

    (65)

    • A.①②③   
    • B.①②④  
    • C.②③④  
    • D.①③④    合同变更控制系统规定合同修改的过程,包括(66) 。    ①文书工作 ②跟踪系统 ③争议解决程序 ④合同索赔处理    (66)
    • A.①②③   
    • B.②③④   
    • C.①②④      
    • D.①③④
  10.  ● 甲公司承担的某系统开发项目,在进入开发阶段后,出现了一系列质量问题。为此,项目经理召集项目团队,列出问题,并分析问题产生的原因。结果发现,绝大多数的问题都是由几个原因造成的,项目组有针对性地采取了一些措施。这种方法属于

    (67)法。

    (67)

    • A.因果图   
    • B.控制图   
    • C.排列图       
    • D.矩阵图