一起答
单选

(66)是指对拟实施项目技术上的先进性、适用性,经济上的合理性、盈利性,以及实施上的可能性和风险可控性进行全面科学的综合分析,为项目决策提供客观依据的一种技术经济研究活动。

  • A.项目论证
  • B.项目评估
  • C.项目识别
  • D.项目可行性分析
参考答案
查看试卷详情
相关试题
  1. (75) is the budgeted amount for the work actually completed on the schedule activity or WBS component during a given time period.

    • A.Planned value
    • B.Actual cost
    • C.Earned value
    • D.Cost variance
  2. (72) is the process of obtaining the stakeholdrs'formal acceptance of the completed project scope. Verifying the scope includes reviewing deliverables and work results to ensure that all were completed satisfactorily.

    • A.WBS Creation
    • B.Scope definition
    • C.Project acceptance
    • D.Scope verification
  3. During the risk analysis process, it is determined that one identified risk event cannot be avoided, mitigated, or insured. This risk event is a critical item that could cause the project to fail if it occurs. The best option for the project manager is to: (73).

    • A.Continue to search for an insurance company that would assume the risk
    • B.Place special emphasis on the risk event to intensely manage that item and all interfacing items
    • C.Play down the risk and the team will find a means of overcoming any failure
    • D.Ignore the risk assessment because any assigned value is a point estimate which is never precisely the expected state of nature
  4. Estimating activity durations uses information on activity scope of (74), required resource types, estimated resource quantities, and resource calendars.

    • A.milestone
    • B.work
    • C.quality
    • D.baseline
  5. 以下不属于全面质量管理(TQM)核心特征的是(70)。

    • A.全面计划的质量管理
    • B.全面结果的质量管理
    • C.全过程的质量管理
    • D.全员参加的质量管理
  6. Most system development methodologies also provide (71), whose purpose is to contain the various pieces of relevant information-feasibility assessments, schedules, needs analysis, and so forth-in a single place so that they can be presented to project clients and other related parties.

    • A.statement of work
    • B.project planning
    • C.baseline plan
    • D.information system planning
  7. 以下关于项目最终验收的描述中,错误的是(68)。

    • A.在系统经过试运行以后的约定时间,双方可以进行项目的最终验收工作
    • B.对于中小型项目,可以将系统测试和最终验收合并进行,并对验收过程加以确认
    • C.对于信息系统而言,最终验收标志着项目的结束和售后服务的开始
    • D.项目最终验收合格后,应由承建方项目组撰写验收报告并提请建设方工作主管认可
  8. 在对某项目采购供应商的评价中,评价项有:对需求的理解、技术能力、管理水平、企业资质和类似项目经验等。假定每个评价项满分为10分,其中“类似项目经验”权重为10%。若4个评定人在“类似项目经验”项的打分分别为7分、8分、7分、6分,那么该供应商的“类似项目经验”的单项综合分为(69)。

    • A.0.7
    • B.1.4
    • C.7
    • D.28
  9. 通常,用于编制采购计划过程的技术、方法不包括(67)。

    • A.自制或外购决策
    • B.合同类型的选择
    • C.专家判断
    • D.制订方案邀请书(RFP)
  10. 通常,变更控制流程的作用不包括(65)。

    • A.列出要求变更的手续
    • B.记录要求变更的事项
    • C.描述管理层对变更的影响
    • D.确定要批准还是否决变更请求