一个有两个作业管理进程的批处理系统,作业调度采用最高响应比优先的算法,进程调度采用基于优先数(优先数大表示优先级别高)的算法。有以下作业序列:

作业F的运行结束时间为(26)(假定在作业运行期间,除了有空闲的作业管理进程以外,系统不进行调度工作)。

  • A.14:50
  • B.15:30
  • C.13:40
  • D.13:10
参考答案
查看试卷详情
相关试题
  1. (79)

    • A.gain
    • B.gained
    • C.gains
    • D.gaining
  2. (78)

    • A.insiders
    • B.money
    • C.outsiders
    • D.warehouse
  3. (77)

    • A.close
    • B.closed
    • C.enclose
    • D.enclosed
  4. Soon, more of the information we receive via the Internet could come(71)in digital wrappers.

    Wrappers are made up(72)software code that's targeted to do specific things with the data(73)within them, such as helping to define queries for search engines. They also keep(74)from(75)access to that code.

    • A.package
    • B.packaged
    • C.packages
    • D.packaging
  5. (76)

    • A.of
    • B.off
    • C.on
    • D.out
  6. (73)

    • A.college
    • B.family
    • C.workshop
    • D.cottage
  7. (74)

    • A.plan
    • B.schedule
    • C.effort
    • D.product
  8. Developing reliable software on time and within(66)represents a difficult endeavor for many organizations.

    Usually business solutions have three main aspects: people,(67),and technology. The main reason for failing software projects has little to do with technology and tools, and much to do with lack of process(68). Experience has shown that introducing new technology and tools in an immature or undisciplined environment is likely to increase the chaos. CASE tools are not enough. "A fool with a tool is still a fool !"

    Structured method was the first wave of the software industry. This was the beginning of transforming software development from a"(69)industry" to mass production. Software process movement if the second wave in the software industry. The process maturity movement prepares the way for the third wave of the software industry :"software industrialization". Software development will become like an assembly and manufacturing process. A cfiticalenabling factor is adisciplined software engineering . process with predictable quality,(70)and functionality.

    • A.forecast
    • B.preparation
    • C.budget
    • D.economy
  9. (71)

    • A.process
    • B.skill
    • C.organization
    • D.interface
  10. (72)

    • A.law
    • B.discipline
    • C.plan
    • D.evaluation