项目经理小李对某活动工期进行估算时,发现人员的熟练程度和设备供应是否及时对工期至关重要。如果形成最有利组合时,预计9天可以完成;如果形成最不利组合时,预计23天可以完成;按照公司的正常情况,一般13天可以完成。该项目的工期可估算为()天。
The customer asks your project to be completed 6 months earlier than planned.You think this target can be reached by-overlapping project activities. This approach is known as ().
The auditing function that provides feedback about the quality of output is referred to as ().
()is not included in the main contents of the operation and maintenance of the information system.
WLAN is increasingly popular because it enables cost-effective () among people and applications that were not possible in the past.
In project time management, activity definition is the process of identifying and documenting the specific action to be performed to produce the project deliverables. ()are not output of activity definition.
在质量控制过程中,经常会使用一些工具和方法。(1)是一种基于80/20原理,用于找出影响项目产品或服务质量的主要因素的方法。(2)不属于质量控制活动。
知识产权作为法律所确认的知识产品所有人依法享有的民事权利,其管理的要项中不包括()。
在制定项目质量计划过程中,可以采用()方法以识别哪些因素会对特定变量产生影响。
配置项的状态可分为“草稿”、“正式”和“修改”三种。以下关于配置项状态的叙述中,不正确的是:()。
以下关于质量管理的叙述中,不正确的是:()。
高级经济师考试试题精选练习(1)
高级经济师考试模拟练习题之单选题(1
高级经济师考试试题精选练习(2)
高级经济师考试试题精选练习(3)
高级经济师考试试题:经济法案例试题精
高级经济师考试模拟试题及答案
高级经济师考试试题及答案:单选练习题
高级经济师考试试题:经济法案例试题精
高级经济师考试模拟题及答案练习(1)
高级经济师考试模拟题及答案练习(2)