单选

●拟采购货物的规格、标准统一,现货货源充足且价格变化幅度小的政府采购项目,可以依照《中华人民共和国政府采购法>采用(16)方式进行采购。

(16)

  • A.竞争性谈判采购   
  • B.邀请招标
  • C.单一来源采购   
  • D.询价
参考答案
查看试卷详情
相关试题
  1. ● Which of the following Project Scope Management processes involves subdividing the major project deliverables into smaller, more manageable components? (74)

     (74)

    • A. Scope Planning
    • B. Scope Verification
    • C. Scope Change Control
    • D. Scope Definition
  2. ● The work breakdown structure comprises several levels of decomposition of the total project. The lowest level of definition is always the (75) .

     (75)

    • A. planning element
    • B.work package
    • C.subtask
    • D. working interface
  3. ●A project manager is called to an informal meeting with the customer and a problem is raised. This problem has major implications for the project manager's company, but the customer wants to pursue a solution at the meeting.The project manager should (72) .

    (72)

    • A. tell the customer that he will not address any problems becausethis is only an information exchange meeting
    • B. tell the customer that the problem is not sufficiently defined to determine the appropriate action
    • C. collect as much information on the problem without committing his company to a solution
    • D. give the customer a range of solutions that might be acceptable to his Company
  4. ●The project manager must maintain an effective communication link with the customer's satisfaction with the progress of the project. The project manager maintains this link through (71).

    (71)

    • A.periodic project reports, periodic visits to the customer, and telephonic exchanges
    • B.subordinates, project team members, and the project sponsor
    • C.one-time reports, weekly reports, and monthly reports
    • D.the telephone, facsimile, and data transmission
  5. ● The project schedule is more than a document that lays out the activities over time to represent the time dimension of the project, it is a management tool to be used for decision making. As such, the schedule is used by the project management team to (73) .

     (73)

    • A. measure, delay, record, distribute, analyze, and direct
    • B. plan, schedule, monitor, control, report, and forecast
    • C. promote, highlight, monitor, control, forecast, and report
    • D. emphasize, visualize, analyze, conceptualize, report, and record
  6. ●某系统集成公司制订了一系列完备的质量管理制度,其中一项是要求每个项目在各个阶段的最后都必须进行质量审计。这种审计活动是(70)过程的一部分工作。

    (70)

    • A.质量保证   
    • B.质量改进
    • C.质量控制   
    • D.质量计划
  7. ●在项目管理中经常需要在成本与进度之间做出权衡,尽管聘用高级程序员的花费要比初级程序员高得多,却可以获得更高的生产效率。如果项目经理在编制项目质量计划时,希望确定聘用高级程序员和初级程序员的最佳人数比例,同时还要明确质量标准以及达到标准的最佳方法,最适合采用的方法是 (69)。

    (69)

    • A.基准比较
    • B.效益/成本分析
    • C.实验设计   
    • D.质量成本分析
  8. ●在进行项目质量控制时,统计方法强调一切用数据说话,而(67)则主要用事实说话,靠“灵感”发现新思想、解决新问题。

    (67)

    • A.帕累托图   
    • B.树状图
    • C.相互关系图 
    • D.亲和图
  9. ●某项目质量管理员希望采用一些有助于分析问题发生原因的工具,来帮助项目组对各(68)出现的质量问题进行预测并制订应对措施。以下工具中,能够满足其需要的是(68)。

    (68)

    • A.控制图   
    • B.流程图
    • C.树状图
    • D.活动网络图
  10. ●配置项的版本号规则与配置项的状态相关,以下叙述中正确的是(66)。

    (66)

    • A.处于“正式”状态的配置项版本号格式为x.Y,当配置项升级幅度较大时,可以将变动部分制作为配置项的附件,附件版本依次为1.0,1.1,……
    • B.处于“修改”状态的配置项版本号格式为X.YZ,其中X保持不变,YZ在01~99之间递增
    • C.处于“草稿”状态的配置项版本号格式为0.YZ,随着草稿的修正,YZ取值逐渐递增,而YZ的初值和幅值由用户自行把握
    • D.处于“草稿”状态的配置项版本号格式为x.YZ,当配置项通过评审,状态第一次成为“正式”时,版本号直接设置为1.0