( )不是进度计划调整的程序。

  • A.发现工程进度严重偏离计划时,总监理工程师应及时签发《监理通知》,并组织监理工程师分析原因、研究措施
  • B.召开各方面协调会议,研究应采取的措施,保证合同约定目标的实现
  • C.必须延长工期时,承建单位应填报《工程延期申请表》,报工程监理部审查
  • D.分析承建单位主要开发人员的能力等方面的配套安排
参考答案
查看试卷详情
相关试题
  1. The difference value between Budgeted Cost for work Performed and Actual Cost for Work Performed is( ).

    • A.Cost Variance
    • B.Schedule Variance
    • C.Earned Value
    • D.Cost Performed Index
  2. ( )must be between on-line deployment and final acceptance.

    • A.Detailed design
    • B.Test run
    • C.Internal testing
    • D.Contract signing
  3. ( )is used to model aggregates of information and the relationships these aggregates have to other.

    • A.Data flow diagram
    • B.Entity relationship diagram
    • C.Sequence diagram
    • D.Structure diagram
  4. In software engineering the design phase is divided into( )。

    • A.system design and detailed design
    • B.computer design and program design
    • C.system design and hardware design
    • D.computer design and detailed design
  5. 项目协调的监理方法主要包括( )

    ①监理会议  ②监理报告  ③沟通  ④规划

    • A.①②③④
    • B.①②③
    • C.①②④
    • D.①③④
  6. Most operating systems have a standard set of ( ) to handle the processing of all input and output instructions.

    • A.spreadsheet
    • B.control instructions
    • C.I/O operation
    • D.data table
  7. 《监理通知单》属于发送给( )的文档。

    • A.承建单位
    • B.建设单位
    • C.监理单位
    • D.分包单位
  8. 指令文件是表达( )对承建单位提出指示或命令的书面文件。

    • A.监理单位
    • B.总工程师
    • C.监理工程师
    • D.业主代表
  9. ( )属于监理内部文档。

    • A.监理规划
    • B.监理实施细则
    • C.监理工作日志
    • D.监理通知单
  10. 备份与恢复是一种数据安全策略,通过备份软件把数据备份到光盘或移动硬盘上,在原始数据丢失或遭到破坏的情况下,利用备份数据把原始数据恢复出来,使系统能够正常工作。数据备份的策略主要有全备份、差分备份、增量备份和( )。

    • A.软件备份
    • B.人工备份
    • C.备份介质轮换
    • D.双机容错