● 某视频监控项目需要布 51 个监控点,承建方计划分三组(组内人员入场时间、分工各有不同)同时实施,项目经理提交了按时间顺序实施的进度计划交由监理审核:挖基坑、立桩需要 17 天(a) ,设备采购到货需要 15 天(b) ,设备安装需要 8.5 天(每组安装 1 套设备需要 0.5天) (c) ,模块测试需要 8.5 天(每组测试 1 套设备需要 0.5 天)(d) ,系统联调需要 2 天(e) ,验收需要 2 天(f) 。监理审核后认为,采用(46)并行施工策略,实际工期最短,是(47)天。
(46)
● Maintenance activities include(74).
①making enhancements to software products
②developing a new software product
③correcting problems
④adapting products to new environments
(74)
● A quality assurance team should be(75).
①associated with any particular development group
②depended upon any particular development group
③responsible for reporting directly to management
④in-depended upon any particular development group
(75)
● A well-designed system should be(73).
①easily understood
②reliable
③straightforward to implement
④straightforward to maintain
(73)
● The process of software development doesn’t include(72) .
(72)
● Consumption of the total life-cycle effort in software maintenance is (71) that in software development.
(71)
● 监理规划编制的依据为(69) 。
(69)
● 监理单位在业主开始委托监理的过程中,为承揽监理业务而编写的监理方案性文件是(70) 。
(70)
● 工程监理人员发现信息工程设计不符合相关工程质量标准或者合同约定的质量要求时, (68) 。
(68)
● 旁站监理是指监理人员在工程施工阶段监理中,对(67)的施工质量实施现场跟班的监督活动。
(67)
● 关于监理质量控制,不正确的是(66) 。
(66)
高级经济师考试试题精选练习(1)
高级经济师考试模拟练习题之单选题(1
高级经济师考试试题精选练习(2)
高级经济师考试试题精选练习(3)
高级经济师考试试题:经济法案例试题精
高级经济师考试模拟试题及答案
高级经济师考试试题及答案:单选练习题
高级经济师考试试题:经济法案例试题精
高级经济师考试模拟题及答案练习(1)
高级经济师考试模拟题及答案练习(2)