一起答
单选

A公司承接了某银行网上银行系统的建设项目,包括应用软件开发、软硬件集成适配、系统运维等多项工作内容。针对该项目,不正确的是:()。

  • A.该项目的干系人包括客户、公司高层领导、项目成员及网上银行用户
  • B.干系人管理工作应由该项目成员分工负责
  • C.干系人管理有助于为项目赢得更多的资源
  • D.通常来说,干系人对项目的影响能力在项目启动阶段最大,随着项目的进展逐渐减弱
参考答案
查看试卷详情
相关试题
  1. The process of translating the qualitymangement plan into executable quality activities that incorporate theorganization's quality policies into the project.

    • A.Manage quality
    • B.Quality audit
    • C.Quality metrics
    • D.Quality improvement
  2. Includes the processes required to ensure that the project includes all the work required , and only the work required , to compete the project successfully . managing the project scope is primarily concerned with defining and controlling what is not included in the project.

    • A.Create scope
    • B.Project stakeholder management
    • C.Preject scope management
    • D.Project cost management
  3. Estimate activity durations is the processof estimating the number of work periods to complete indivities with estimatedresources . the tools and technques is not including().

    • A.expert judgment
    • B.analogous estimating
    • C.requiremen tstraceability matrix
    • D.three-point estimating
  4. Is the technology that appears to emulate human performancetypicaliy by learning,coming to its own conclusions, appearing to understandcomplex content, engaging in natural dialogs with people, enhancing humancognittive performance (also known as cognittive computing) or replacing peopleon execution ofnonroutine tasks().

    • A.Cloud service
    • B.Blockchain
    • C.Internet of things
    • D.Artificial intellingence
  5. Is a decentralized, distributed and public digital ledger that is used to record transactions across many computers so that the record cannot be alterred retroactively without the alteration of all subsequent blocks and the collusion ?of the network().

    • A.Cloud service
    • B.Blockchain
    • C.Internet of things
    • D.Artificial intellingence
  6. 某拟建项目财务净现金流量如下表所示,该项目的静态投资回收期是()年。

    • A.5.4
    • B.5.6
    • C.7.4
    • D.7.6
  7. 某项目由并行的3个活动甲、乙和丙组成,为活动甲分配3人5天可以完成,活动乙分配6人7天可以完成,活动丙分配4人2天可以完成,活动完成后人员可再调配。在此情况下,项目最短工期为()天。

    • A.6
    • B.7
    • C.8
    • D.9
  8. 某项目由并行的3个活动甲、乙和丙组成,为活动甲分配3人5天可以完成,活动乙分配6人7天可以完成,活动丙分配4人2天可以完成,活动完成后人员可再调配。在此情况下,此时人员最少配置为()。

    • A.6
    • B.9
    • C.10
    • D.13
  9. 质量管理实施阶段的工具与技术不包括()。

    • A.储备分析
    • B.统计抽样
    • C.过程决策程序图
    • D.质量审计
  10. 某项工程的活动明细如下表(时间:周:费用:万元):项目总预算由原先的60万元增加到63万元,根据上表,所需项目总费用为()万元。

    • A.60
    • B.64
    • C.56
    • D.45