小李作为项目经理需要从以下四个项目方案中选择项目,已知项目周期均为2年且期初投资额都是30.000元,折现均为10%。项目情况如下:方案A:第一年现金流为14,000元,第二年现金流19,000元方案B:第一年现金流为23,000元,第二年现金流20,000元方案C:第一年现金流为18,000元,第二年现金流24,000元方案D:第一年现金流为21,000元,第二年现金流22,000元则小李应该优先选择()。

  • A.方案A
  • B.方案B
  • C.方案C
  • D.方案D
参考答案
查看试卷详情
相关试题
  1. The process of translating the qualitymangement plan into executable quality activities that incorporate theorganization's quality policies into the project.

    • A.Manage quality
    • B.Quality audit
    • C.Quality metrics
    • D.Quality improvement
  2. Includes the processes required to ensure that the project includes all the work required , and only the work required , to compete the project successfully . managing the project scope is primarily concerned with defining and controlling what is not included in the project.

    • A.Create scope
    • B.Project stakeholder management
    • C.Preject scope management
    • D.Project cost management
  3. Estimate activity durations is the processof estimating the number of work periods to complete indivities with estimatedresources . the tools and technques is not including().

    • A.expert judgment
    • B.analogous estimating
    • C.requiremen tstraceability matrix
    • D.three-point estimating
  4. Is the technology that appears to emulate human performancetypicaliy by learning,coming to its own conclusions, appearing to understandcomplex content, engaging in natural dialogs with people, enhancing humancognittive performance (also known as cognittive computing) or replacing peopleon execution ofnonroutine tasks().

    • A.Cloud service
    • B.Blockchain
    • C.Internet of things
    • D.Artificial intellingence
  5. Is a decentralized, distributed and public digital ledger that is used to record transactions across many computers so that the record cannot be alterred retroactively without the alteration of all subsequent blocks and the collusion ?of the network().

    • A.Cloud service
    • B.Blockchain
    • C.Internet of things
    • D.Artificial intellingence
  6. 某拟建项目财务净现金流量如下表所示,该项目的静态投资回收期是()年。

    • A.5.4
    • B.5.6
    • C.7.4
    • D.7.6
  7. 某项目由并行的3个活动甲、乙和丙组成,为活动甲分配3人5天可以完成,活动乙分配6人7天可以完成,活动丙分配4人2天可以完成,活动完成后人员可再调配。在此情况下,项目最短工期为()天。

    • A.6
    • B.7
    • C.8
    • D.9
  8. 某项目由并行的3个活动甲、乙和丙组成,为活动甲分配3人5天可以完成,活动乙分配6人7天可以完成,活动丙分配4人2天可以完成,活动完成后人员可再调配。在此情况下,此时人员最少配置为()。

    • A.6
    • B.9
    • C.10
    • D.13
  9. 质量管理实施阶段的工具与技术不包括()。

    • A.储备分析
    • B.统计抽样
    • C.过程决策程序图
    • D.质量审计
  10. 某项工程的活动明细如下表(时间:周:费用:万元):项目总预算由原先的60万元增加到63万元,根据上表,所需项目总费用为()万元。

    • A.60
    • B.64
    • C.56
    • D.45