● 风险的成本估算完成后,可以针对风险表中的每个风险计算其风险曝光度。某软件小组计划项目中采用 50 个可复用的构件,每个构件平均是 100LOC,本地每个 LO的成本是13元人民币。下面是该小组定义的一个项目风险:

1. 风险识别:预定要复用的软件构件中只有 50%将被集成到应用中,剩余功能必

须定制开发;

2. 风险概率:60%;

3. 该项目风险的风险曝光度是 (62) 。

  • A. 32500   
  • B. 65000   
  • C. 1500    
  • D. 19500
试题出自试卷《2006年下半年《信息系统项目管理师》上午试题(参考答案版)》
参考答案
查看试卷详情
相关试题
  1. ● (73) is a category assigned to products or services having the samefunctional use but different technical characteristics. It is not same asquality.

    • A.Problem    
    • B.Grade    
    • C.Risk     
    • D.Defect
  2.    ● Project  (74) Management is the Knowledge Area that employs the processes required to ensure timely and appropriate generation, collection, distribution, storage, retrieval, and ultimate disposition of project information.  

    • A.Integration      
    • B.Time          
    • C.Planning      
    • D.Communication 
  3.  ● The (75) process analyzes the effect of risk events and assigns a numerical rating to those risks. 

    • A.Risk Identification               
    • B.Quantitative Risk Analysis 
    • C.Qualitative Risk Analysis            .Risk Monitoring and Control 
  4. ● Project Quality Management must address the management of the projecand the (72) of the project. While Project Quality Management applies to alprojects, regardless of the nature of their product, product quality measureand techniques are specific to the particular type of product produced by thproject.

    • A.performance  
    • B.process   
    • C.product   
    • D.object
  5. ● In approximating costs, the estimator considers the possible causes ovariation of the cost estimates, including(71) 。

    • A.budget     
    • B.plan     
    • C.risk     
    • D.contract
  6. ● In the project management context, (68) includes characteristics of unification, consolidation, articulation, and integrative actions that are crucial to project completion, successfully meeting customer and other stakeholder requirements, and managing expectations.

    • A.integration  
    • B.scope    
    • C.process   
    • D.charter
  7. ● Project (69) Management includes the processes required to ensure thatthe project includes all the work required, and only the work required, tocomplete the project successfully.

    t

    • A.Integration  
    • B.Scope  
    • C.Configuration  
    • D.Requiremen
  8. ● On some projects, especially ones of smaller scope, activity sequencing, activity resource estimating, activity duration estimating, and (70) are so tightly linked that they are viewed as a single process that can be performed by a person over a relatively short period of time.

    • A.time estimating      
    • B.cost estimating
    • C.project planning     
    • D.schedule development
  9. ● Organizations perform. work to achieve a set of objectives. Generally,work can be categorized as either projects or operations, although the twosometimes are (67) .

    • A.confused   
    • B.same     
    • C.overlap   
    • D.dissever
  10. ● (66) from one phase are usually reviewed for completeness and accuracyand approved before work starts on the next phase.

    • A.Process    
    • B.Milestone  
    • C.Work   D.
    • Deliverables