单选

 ● 一般将成本管理划分为成本估算、成本预算、成本控制几个过程。以下关于成 本预算的描述,不正确的是 (38 ) 。 

  • A.当项目的 具体工作无法确定时,无法进行成本预算 
  • B.成本基准计划可以作为度量项目绩效 依据 
  • C.管理储备是为范围和成本 潜在变化而预的预算,因此需要体现在项目成本基线里 
  • D.成本预算过程完成后,可能会引起项目管理计划  的更新 
试题出自试卷《2006年下半年《信息系统项目管理师》上午试题(标准答案+解析版)》
参考答案
查看试卷详情
相关试题
  1.  ● The (75) process analyzes the effect of risk events and assigns a numerical rating to those risks. 

    • A.Risk Identification               
    • B.Quantitative Risk Analysis 
    • C.Qualitative Risk Analysis            .Risk Monitoring and Control 
  2. ● (73) is a category assigned to products or services having the samefunctional use but different technical characteristics. It is not same asquality.

    • A.Problem    
    • B.Grade    
    • C.Risk     
    • D.Defect
  3.    ● Project  (74) Management is the Knowledge Area that employs the processes required to ensure timely and appropriate generation, collection, distribution, storage, retrieval, and ultimate disposition of project information.  

    • A.Integration      
    • B.Time          
    • C.Planning      
    • D.Communication 
  4. ● Project Quality Management must address the management of the projecand the (72) of the project. While Project Quality Management applies to alprojects, regardless of the nature of their product, product quality measureand techniques are specific to the particular type of product produced by thproject.

    • A.performance  
    • B.process   
    • C.product   
    • D.object
  5. ● On some projects, especially ones of smaller scope, activity sequencing, activity resource estimating, activity duration estimating, and (70) are so tightly linked that they are viewed as a single process that can be performed by a person over a relatively short period of time.

    • A.time estimating      
    • B.cost estimating
    • C.project planning     
    • D.schedule development
  6. ● In approximating costs, the estimator considers the possible causes ovariation of the cost estimates, including(71) 。

    • A.budget     
    • B.plan     
    • C.risk     
    • D.contract
  7. ● Project (69) Management includes the processes required to ensure thatthe project includes all the work required, and only the work required, tocomplete the project successfully.

    t

    • A.Integration  
    • B.Scope  
    • C.Configuration  
    • D.Requiremen
  8. ● In the project management context, (68) includes characteristics of unification, consolidation, articulation, and integrative actions that are crucial to project completion, successfully meeting customer and other stakeholder requirements, and managing expectations.

    • A.integration  
    • B.scope    
    • C.process   
    • D.charter
  9. ● (66) from one phase are usually reviewed for completeness and accuracyand approved before work starts on the next phase.

    • A.Process    
    • B.Milestone  
    • C.Work   D.
    • Deliverables
  10. ● Organizations perform. work to achieve a set of objectives. Generally,work can be categorized as either projects or operations, although the twosometimes are (67) .

    • A.confused   
    • B.same     
    • C.overlap   
    • D.dissever