● Which statement about the preliminary design stage of a software development project is true? (75) .
(75)
● You are a project manager for a small project. Your project was budgeted for ¥500,000 over a six-week period. As of today, you've spent ¥260,000 of your budget to complete work that you originally expected to cost ¥280,000. According to your schedule, you should have spent ¥300,000 by this point. Based on these circumstances, your project could be BEST described as (74) .
(74)
● A work breakdown structure (WBS) is a tool used to define and group a project's discrete work elements in a way that helps organize and define the total work scope of the project. A WBS is most useful for(72) .
(72)
● Sub-contractors should obey the contractor in information system project. When censoring sub-contractors, the supervisor mostly concerns about (73).
(73)
● 以下做法正确的是(70) 。
(70)
● 10BaseT is an Ethernet LAN term meaning a maximum transfer rate of 10Mbps that uses baseband signaling and twisted pair cabling. A 10BaseT Ethernet LAN has a (71) topology.
(71)
● 在监理组织协调过程中,以下行为,(69)不能够较好体现公平、公正、独立的原则。
(69)
● 根据《国家电子政务工程项目档案管理暂行办法》,下列文档中,(68)不必列入电子政务验收文档范围。
(68)
● 工程监理验收报告主体内容应包括(67) 。
(67)
● 信息系统安全管理体系中,数据安全的目标不包括(64) 。
(64)
2017年软考中级多媒体应用设计师模
2017年软考中级多媒体应用设计师模
2017年软考中级多媒体应用设计师模
2006年上半年《多媒体应用设计师》
2007年下半年《多媒体应用设计师》
2008年下半年《多媒体应用设计师》
2010年5月份软考《多媒体应用设计
2011年上半年多媒体应用设计师下午
2011年上半年多媒体应用设计师下午
2012年上半年软考《多媒体应用设计