  1.  ● The (75) process analyzes the effect of risk events and assigns a numerical rating to those risks. 

    • A.Risk Identification               
    • B.Quantitative Risk Analysis 
    • C.Qualitative Risk Analysis            .Risk Monitoring and Control 
  2. ● (73) is a category assigned to products or services having the samefunctional use but different technical characteristics. It is not same asquality.

    • A.Problem    
    • B.Grade    
    • C.Risk     
    • D.Defect
  3.    ● Project  (74) Management is the Knowledge Area that employs the processes required to ensure timely and appropriate generation, collection, distribution, storage, retrieval, and ultimate disposition of project information.  

    • A.Integration      
    • B.Time          
    • C.Planning      
    • D.Communication 
  4. ● Project Quality Management must address the management of the projecand the (72) of the project. While Project Quality Management applies to alprojects, regardless of the nature of their product, product quality measureand techniques are specific to the particular type of product produced by thproject.

    • A.performance  
    • B.process   
    • C.product   
    • D.object
  5. ● On some projects, especially ones of smaller scope, activity sequencing, activity resource estimating, activity duration estimating, and (70) are so tightly linked that they are viewed as a single process that can be performed by a person over a relatively short period of time.

    • A.time estimating      
    • B.cost estimating
    • C.project planning     
    • D.schedule development
  6. ● In approximating costs, the estimator considers the possible causes ovariation of the cost estimates, including(71) 。

    • A.budget     
    • B.plan     
    • C.risk     
    • D.contract
  7. ● Project (69) Management includes the processes required to ensure thatthe project includes all the work required, and only the work required, tocomplete the project successfully.

    t

    • A.Integration  
    • B.Scope  
    • C.Configuration  
    • D.Requiremen
  8. ● In the project management context, (68) includes characteristics of unification, consolidation, articulation, and integrative actions that are crucial to project completion, successfully meeting customer and other stakeholder requirements, and managing expectations.

    • A.integration  
    • B.scope    
    • C.process   
    • D.charter
  9. ● (66) from one phase are usually reviewed for completeness and accuracyand approved before work starts on the next phase.

    • A.Process    
    • B.Milestone  
    • C.Work   D.
    • Deliverables
  10. ● Organizations perform. work to achieve a set of objectives. Generally,work can be categorized as either projects or operations, although the twosometimes are (67) .

    • A.confused   
    • B.same     
    • C.overlap   
    • D.dissever