某工程计划如图6-3所示,弧上的标记为作业编码及其需要的完成时间(天),作业F最迟开始时间需在第(6)天开始。

  • A.8
  • B.12
  • C.13
  • D.17
试题出自试卷《软件水平考试(中级)网络工程师上午(基础知识)试题模拟试卷18》
参考答案
查看试卷详情
相关试题
  1. (136)

    • A.path
    • B.rout
    • C.circuit
    • D.way
  2. (134)

    • A.collision
    • B.congestion
    • C.drop
    • D.delay
  3. (135)

    • A.flow
    • B.admission
    • C.traffic
    • D.time
  4. (133)

    • A.packets
    • B.cells
    • C.message
    • D.files
  5. In low-speed network, it is usually adequate to wait for congestion to occur and then react to it by telling the source of packets to slow down. In high-speed networks, this approach often works poorly, because in the(71)between sending the notification and notification arriving at the source, thousands of additional(72)may arrive. In ATM network, a major tool for preventing(73)is(74)control. When a host wants a new virtual(75),it must describe the traffic to be offered and the service expected.

    • A.interval
    • B.time
    • C.slot
    • D.delay
  6. (131)

    • A.quality
    • B.Traffic
    • C.services
    • D.route
  7. (130)

    • A.flow table
    • B.flow label
    • C.rout table
    • D.Tag table
  8. (129)

    • A.source
    • B.resources
    • C.route
    • D.Entry
  9. To a router, a flow is a(66)of packets that share the same Characterstics, such as traveling the same(67),using the same(68),having the same kind of security, and so on. A router that supports the handling of flow labels has a(69)table. The table has an entry for each active flow label; each entry defines the(70)required by the corresponding flow label.

    • A.sequence
    • B.stream
    • C.Queues
    • D.flow
  10. (128)

    • A.path
    • B.rout
    • C.circuit
    • D.way