一项网络工程的建设流程通常由

①对现有网络的体系结构进行分析,

②网络需求分析,

③确定网络物理结构,

④确定网络逻辑结构,

⑤安装、测试和维护等5阶段组成,

根据网络开发设计的过程,对这5个阶段的先后排序正确的是()。

  • A.①②③④⑤
  • B.②①④③⑤
  • C.①②④③⑤
  • D.②①③④⑤
试题出自试卷《软件水平考试(中级)网络工程师上午(基础知识)试题模拟试卷18》
参考答案
查看试卷详情
相关试题
  1. (136)

    • A.path
    • B.rout
    • C.circuit
    • D.way
  2. (134)

    • A.collision
    • B.congestion
    • C.drop
    • D.delay
  3. (135)

    • A.flow
    • B.admission
    • C.traffic
    • D.time
  4. (133)

    • A.packets
    • B.cells
    • C.message
    • D.files
  5. In low-speed network, it is usually adequate to wait for congestion to occur and then react to it by telling the source of packets to slow down. In high-speed networks, this approach often works poorly, because in the(71)between sending the notification and notification arriving at the source, thousands of additional(72)may arrive. In ATM network, a major tool for preventing(73)is(74)control. When a host wants a new virtual(75),it must describe the traffic to be offered and the service expected.

    • A.interval
    • B.time
    • C.slot
    • D.delay
  6. (131)

    • A.quality
    • B.Traffic
    • C.services
    • D.route
  7. (130)

    • A.flow table
    • B.flow label
    • C.rout table
    • D.Tag table
  8. (129)

    • A.source
    • B.resources
    • C.route
    • D.Entry
  9. To a router, a flow is a(66)of packets that share the same Characterstics, such as traveling the same(67),using the same(68),having the same kind of security, and so on. A router that supports the handling of flow labels has a(69)table. The table has an entry for each active flow label; each entry defines the(70)required by the corresponding flow label.

    • A.sequence
    • B.stream
    • C.Queues
    • D.flow
  10. (128)

    • A.path
    • B.rout
    • C.circuit
    • D.way