● 项目组成员中有一名专职的文件管理员,其主要职责之一是负责项目组的文件收发和保管。针对于文件收发环节,以下叙述不正确的是(65) 。
(65)
● Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the (75) level.
(75)
● Configuration management system can be used in defining approval levels for authorizing changes and providing a method to validate approved changes.(74) is not a project configuration management tool.
(74)
● Many useful tools and techniques are used in developing schedule. (72) is a schedule network analysis technique that modifies the project schedule to account for limited resource.
(72)
● Changes may be requested by any stakeholder involved with the project, but changes can be authorized only by (73).
(73)
● Project schedule management is made up of six management processes including: activity definition, activity sequencing, ( 71) , and schedule control by order.
(71)
● 某项目各期的现金流量如表所示:
设贴现率为 10%,则项目的净现值约为(70) 。
(70)
● 某项目投资额为 190 万元,实施后的利润分析如下表所示:
假设贴现率为 0.1,则项目的投资收益率为(68) 。
(68)
● 甲乙丙为三个独立项目,NPV 甲 =12 万元,NPV 乙=15 万元,NPV 丙=18 万元,三个项目的初始投资额相同,并且回收期相同,则应优先选择(69)项目进行投资。
(69)
● 项目组成员中有一名专职的文件管理员,其主要职责之一是负责项目组的文件收发和保管。针对于文件收发环节,以下叙述不正确的是(65) 。
(65)
● 某项目有Ⅰ、Ⅱ、Ⅲ、Ⅳ四项不同任务,恰有甲、乙、丙、丁四个人去完成各项不同的任务.由于任务性质及每人的技术水平不同,他们完成各项任务所需时间也不同,具体如下表所示
项目要求每个人只能完成一项任务,为了使项目花费的总时间最短,应该指派丁完成(67)任务。
(67)
高级经济师考试试题精选练习(1)
高级经济师考试模拟练习题之单选题(1
高级经济师考试试题精选练习(2)
高级经济师考试试题精选练习(3)
高级经济师考试试题:经济法案例试题精
高级经济师考试模拟试题及答案
高级经济师考试试题及答案:单选练习题
高级经济师考试试题:经济法案例试题精
高级经济师考试模拟题及答案练习(1)
高级经济师考试模拟题及答案练习(2)