一起答

2010年下半年软考信息系统项目管理师-上午试题(标准答案+解析版)

  • 卷面总分:75分
  • 浏览次数:0
  • 测试费用:免费
  • 答案解析:是
  • 练习次数:26次
  • 作答时间:150分钟
试卷简介
这套试卷是考试编写组精心编写而成。本书在研究往年真题的基础上,充分把握考试难度,精选相关的试题编辑成书,内容全面,使考生能够从做题中得到更全面的知识和提升,以真正满足考生的考试需求。
部分试题预览
  1.    ● Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the  (75)   level. 

    (75)

    • A.independent resource      
    • B.individual work load 
    • C.work milestone           
    • D.work package 
  2.    ● Configuration management system can be used in defining approval levels for authorizing changes and providing a method to validate approved changes.(74)   is not a project configuration management tool. 

    (74)

    • A.Rational Clearcase        
    • B.Quality Function Deployment
    • C.Visual SourceSafe        
    • D.Concurrent Versions System
  3.    ● Many useful tools and techniques are used in developing schedule. (72)   is a schedule network analysis technique that modifies the project schedule to account for limited resource.

    (72)

    • A.PERT                   
    • B.Resource levelling
    • C.Schedule compression      
    • D.Critical chain method 
  4.    ● Changes may be requested by any stakeholder involved with the project, but changes can be authorized only by (73).

    (73)

    • A.executive IT manager       
    • B.project manger
    • C.change control board        
    • D.project sponsor 
  5.   ● Project schedule management is made up of six management processes including: activity definition, activity sequencing, ( 71) , and schedule control by order.

    (71)

    • A.activity duration estimating, schedule developing, activity resource estimating
    • B . activity resource estimating, activity duration estimating, schedule       development
    • C.schedule developing, activity resource estimating, activity duration estimating
    • D.activity resource estimating, schedule developing, activity duration estimating
  6.  ● 某项目各期的现金流量如表所示:

    设贴现率为 10%,则项目的净现值约为(70) 。

    (70)

    • A.140      
    • B.70         
    • C.34        
    • D.6
  7.    ● 某项目投资额为 190 万元,实施后的利润分析如下表所示:

    假设贴现率为 0.1,则项目的投资收益率为(68) 。

    (68)

    • A.0.34     
    • B.0.41       
    • C.0.58    
    • D.0.67
  8.     ● 甲乙丙为三个独立项目,NPV 甲 =12 万元,NPV 乙=15 万元,NPV 丙=18 万元,三个项目的初始投资额相同,并且回收期相同,则应优先选择(69)项目进行投资。 

    (69)

    • A.甲          
    • B.乙          
    • C.丙         
    • D.甲或乙
  9.     ● 项目组成员中有一名专职的文件管理员,其主要职责之一是负责项目组的文件收发和保管。针对于文件收发环节,以下叙述不正确的是(65) 。 

    (65)

    • A.电子版文件可通过授权系统来控制收发
    • B.对于纸制文件可以采用编号、盖章等方法控制文件的有效性
    • C.发给客户的文件可以不进行文件回收管理
    • D.对现场使用的外来文件可不进行文件收发管理
  10. ● 某项目有Ⅰ、Ⅱ、Ⅲ、Ⅳ四项不同任务,恰有甲、乙、丙、丁四个人去完成各项不同的任务.由于任务性质及每人的技术水平不同,他们完成各项任务所需时间也不同,具体如下表所示

    项目要求每个人只能完成一项任务,为了使项目花费的总时间最短,应该指派丁完成(67)任务。

    (67)

    • A.Ⅰ          
    • B.Ⅱ          
    • C.Ⅲ          
    • D.Ⅳ