一起答
单选

The (75) describes,in detail,the project's deliverables and the work required to create those deliverables.

  • A.product specification
  • B.project requirement
  • C.project charter
  • D.project scope statement
参考答案
查看试卷详情
相关试题
  1. The (75) describes,in detail,the project's deliverables and the work required to create those deliverables.

    • A.product specification
    • B.project requirement
    • C.project charter
    • D.project scope statement
  2. The (73) provides the project manager with the authority to apply organizational resources to project activities.

    • A.project management plan
    • B.project charter
    • C.project human resource plan
    • D.project stakeholders
  3. The (74) technique involves using project characteristics in a mathematical model to predict total project cost models Can be simple or complex.

    • A.reserve analysis
    • B.cost aggregation
    • C.parametric estimating
    • D.funding limit reconciliation
  4. The (72) process analyzes the effect of risk events and assigns a numerical rating to those risks.

    • A.Quantitative Risk Analysis
    • B.Risk Identification
    • C.Qualitative Risk Analysis
    • D.Risk Monitoring and Control
  5. On some projects,especially ones of smaller scope,activity sequencing,activity resource estimating.Activity duration estimating,and (71) are so tightly linked that they are viewed as a single process that can be performed by a person over a relatively short period of time.

    • A.project planning
    • B.time estimating
    • C.cost estimating
    • D.schedule development
  6. (69)不属于项目收尾的工具与技术。

    • A.专家判断
    • B.转移
    • C.项目管理信息系统
    • D.项目管理方法论
  7. 项目经理老许负责一个管理信息系统项目,最近在与客户共同进行的质量审查中发现一个程序模块不符合客户的需求,进行追溯时,也未发现相应的变更请求。最终老许被迫对这一模块进行再设计并重新编程。造成此项返工的原因可能是(70)。

    • A.未进行项目变更管理
    • B.未进行项目需求管理
    • C.未进行项目配置管理
    • D.未进行项目范围确认
  8. 准确和无偏差的数据是量化风险分析的基本要求。可以通过( )来检查人们对项目风险的理解程度。

    • A.风险数据质量评估
    • B.影响图
    • C.敏感性分析
    • D.发生概率与影响评估
  9. 进行风险监控一般会(68)。

    • A.制订应急响应策略
    • B.进行项目可能性分析
    • C.制订风险管理计划
    • D.进行预留管理
  10. 通常,变更控制系统将对(65)执行自动批准。

    • A.客户提出的建议
    • B.突发事件的结果
    • C.项目发起人提出的建议
    • D.由新规则决定的命令