The(  )process ascertains which risks have the potential of affecting the project and documenting the risks’characteristics.

  • A.Risk Identification
  • B.Quantitative Risk Analysis
  • C.Qualitative Risk Analysis
  • D.Risk Monitoring and Control
参考答案
查看试卷详情
相关试题
  1. The earned value technique is a commonly used method of performance measurement.It integrates project scope,schedule,and cost measures to help the project management team assess project performance.If a project’s Cost Performance Index(CPI=EV/AC)value less than 1.0,it means that(  )。

    • A.the cost savings for work completed
    • B.the project is ahead of its planned schedule
    • C.the cost overrun for work completed
    • D.1ess work was completed than was planned
  2. The(  )provides the project manager with the authority to apply organizational resources to project activities。

    • A.project management plan
    • B.project charter
    • C.project human resource plan
    • D.project stakeholders
  3. (  )is ameasurable,verifiable work poduct such as specification,feasibility study report,detail document,or working prototype。

    • A.Deliverable
    • B.Project charter
    • C.Earned value
    • D.Milestone
  4. 根据材料回答2~3题:

    To keep certain information private and secure while providing remote access for employees,many businesses are creating intranets.An intranet is an(  )organizational intemet that is guarded against outside access by a special feature called a firewall(which can be software,hardware, or a combination of the two).

    • A.outside
    • B.external
    • C.internal
    • D.inside
  5. The(  )process ascertains which risks have the potential of affecting the project and documenting the risks’characteristics.

    • A.Risk Identification
    • B.Quantitative Risk Analysis
    • C.Qualitative Risk Analysis
    • D.Risk Monitoring and Control
  6. 完成某信息系统集成项目中的一个最基本的工作单元A所需的时间,乐观的估计需15天,悲观的估计需29天,最可能的估计需19天,按照PERT方法进行估算,项目的工期约为(  )天。

    • A.18
    • B.19
    • C.20
    • D.21
  7. 为了达到产品/服务的质量要求需要付出相应的成本。以下属于质量预防成本的是(  )。

    • A.设计评估费用
    • B.采购检验费用
    • C.返工或维修费用
    • D.质量审计费用
  8. 某项目经理所在的公司从事高科技产品的信息集成工作。该项目经理现要为一个要求使用并集成一些不同的产品规格的新项目确定合适的组织结构,他最可能选择的类型是(  )。

    • A.矩阵型
    • B.项目型
    • C.职能型
    • D.事业部型
  9. 我国国家信息化建设的信息化政策法规体系包括信息技术发展政策、(  )、信息化法规建设等四个方面。

    • A.移动通信业发展政策和信息文化产业政策
    • B.电子商务发展政策和通信产业政策
    • C.信息产业发展政策和电子政务发展政策
    • D.通信产业政策和信息产品制造业政策
  10. 以下关于项目团队激励的叙述,正确的是(  )。

    • A.马斯洛需求理论共分为4个层次,即生理、社会、受尊重和自我实现
    • B.X理论认为员工是积极的,在适当的情况下员工会努力工作
    • C.Y理论认为员工只要有可能就会逃避为公司付出努力去工作
    • D.海兹伯格理论认为激励因素有两种,一是保健卫生,二是激励需求