● 风险紧迫性评估多用于__(69)__中。

(69)

  • A.风险识别&n
  • bsp;  B.定性风险分析   
  • C.定量风险分析   
  • D.风险应对
参考答案
查看试卷详情
相关试题
  1. ● The e

    • ● The earned value technique is a commonly used method of performance measurement. It integrates project scope, cost, and schedule measures to help the project management team assess project performance. If a project’s Schedule Performance Index(SPI=EV/PV
    • B.less work was completed than was planned
    • C.the cost overrun for work completed    
    • D.the cost under-run of performance to date
  2. ● SWOT

    • ● SWOT analysis is a kind of risk identification method. If the project team chose the SO strategy, they should __(75)__.    (75)A.make full use of the advantage and catch the opportunity
    • B.overcome the weakness and catch the opportunity
    • C.make full use of the advantage and reduce the threat
    • D.overcome the weakness and reduce the threat
  3. ● __(73)__

    • are the four major activities of software configuration management.    ①configuration identification&n
    • bsp; ②statement report  ③
    • change control    ④preparation of requirement
    • document  ⑤configuration auditing    (73)A.①②③④  B.①②④⑤   C.①②③⑤   D.②③④⑤
  4. ● Ethernet is the commonly used loc

    • al area network communication protocol. The standard of Ethernet is __(72)__.    (72)A.IEEE 802.1&n
    • bsp; B.IEEE 802.2  
    • C.IEEE 802.3  
    • D.IEEE 802.11
  5. ● TCP/IP communic

    • ● TCP/IP communication protocol contains four layers. From bottom to top, the four layers are __(71)__.    (71)A.network interface layer, internet layer, transport layer and application layer
    • B.internet layer, network interface layer, transport layer and application layer
    • C.network interface layer, transport layer, network interface layer and application layer
    • D.application layer, transport layer, internet layer and network interface layer
  6. ● 风险紧迫性评估多用于__(69)__中。

    (69)

    • A.风险识别&n
    • bsp;  B.定性风险分析   
    • C.定量风险分析   
    • D.风险应对
  7. ● 决策树分析是风险分析过程中的一项常用技术。某企业在项目风险分析过程中,采用了决策树分析方法,并计算出了EMV(期望货币值)。

    以下说法中,正确的是__(70)__。

    (70)A.以上进行的是定量风险分析,根据分析结果应选择修改现有技术方案的路线

    B.以上进行的是定量风险分析,根据分析结果应选择设计新技术方案的路线

    C.以上进行的是定性风险分析,根据分析结果应选择修改现有技术方案的路线

    D.以上进行的是定性风险分析,根据分析结果应选择设计新技术方案的路线

  8. ● 某系统集成企业为做好项目风险管理,给风险定义了3个参数:

    1、风险严重性:指风险对项目造成的危害程度;

    2、风险可能性:指风险发生的几率;

    3、风险系数:是风险严重性和风险可能性的乘积。

    其中,对项目进度延误、工作量偏差的风险严重性等级和风险可行性等级如下表所示:

    假定该企业将风险系数大于等于6的情况定义为红灯状态,需要优先处理,则下列__(68)__的情况属于红灯状态。

    (68)A.进度延误15%,工作量偏差15%,发生几率为0.5

    B.进度延误15%,工作量偏差35%,发生几率为0.2

    C.进度延误25%,工作量偏差15%,发生几率为0.4

    D.进度延误15%,工作量偏差25%,发生几率为0.4

  9. ● 下图所表示的质量控制工具为__(66)__。

    (66)A.散点图法   B.因果图   C.帕累托图   D.控制图

  10. ● 有关风险识别,以下说法不正确的是__(67)__。

    (67)

    • ● 有关风险识别,以下说法不正确的是__(67)__。    (67)A.项目组全体成员参与风险识别
    • B.识别范围覆盖了项目的整个生命周期
    • C.风险管理计划是风险识别的输出
    • D.识别过程中综合运用了多种风险识别的技术和工具